Question: Using the information from the following table, create an AON network activity diagram. a. Calculate each activity TE (rounding to the nearest integer); the total

Using the information from the following table, create an AON network activity diagram.
a. Calculate each activity TE (rounding to the nearest integer); the total duration of the project; its early start, early finish, late start and late finish times; and slack for each activity. Finally, show the project€™s critical path.
Using the information from the following table, create an AON

b. Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the project€™s schedule? Has the duration changed? Is there a new critical path? Show your conclusions.

Activity Preceding activities Best Likely Worst TE 12 15 25 16 30 20 15 15 15 12 15 17 10 14 12 12 15 12 B. C D. E 13 17 19 15 20 11 13 G, H 12 13

Step by Step Solution

3.40 Rating (172 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Total duration of the project is 82 days Critical pat... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

663-B-M-L-P-M (2117).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!