Question: Using the information from the following table, create an AON network activity diagram. a. Calculate each activity TE (rounding to the nearest integer); the total
a. Calculate each activity TE (rounding to the nearest integer); the total duration of the project; its early start, early finish, late start and late finish times; and slack for each activity. Finally, show the projects critical path.
.png)
b. Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the projects schedule? Has the duration changed? Is there a new critical path? Show your conclusions.
Activity Preceding activities Best Likely Worst TE 12 15 25 16 30 20 15 15 15 12 15 17 10 14 12 12 15 12 B. C D. E 13 17 19 15 20 11 13 G, H 12 13
Step by Step Solution
3.40 Rating (172 Votes )
There are 3 Steps involved in it
a Total duration of the project is 82 days Critical pat... View full answer