Question: Use the following problem statement to answer questions 1 - 5 . BK Home, a homebuilding company, plans to build a new shopping center. A
Use the following problem statement to answer questions BK Home, a homebuilding company, plans to build a new shopping center. A consultant for the company has constructed a project network and estimated activity times, in weeks. The consultant found the following critical path: D The expected activity times of A C and D are and weeks. The variances of and are and Round to four decimal places. Note:
What is the expected project completion time?