Question: Use the following problem statement to answer questions 2 6 - 2 9 . The NF homebuilding company plans to build a new shopping center.
Use the following problem statement to answer questions
The NF homebuilding company plans to build a new shopping center. A consultant for the company has constructed a project network and estimated activity times, in weeks. The consultant found the following critical path: The expected activity times of and are and weeks. The variances of and are and Round to four decimal places. Note: