Question: Use the following problem statement to answer questions 2 6 - 2 9 . The NF homebuilding company plans to build a new shopping center.

Use the following problem statement to answer questions 26-29.
The NF homebuilding company plans to build a new shopping center. A consultant for the company has constructed a project network and estimated activity times, in weeks. The consultant found the following critical path: A -> C -> D. The expected activity times of A, C and D are 11,8, and 5 weeks. The variances of A, C and D are 4,2, and 1. Round to four decimal places. [Note: z =(X-t)/\sigma ]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock