Question: Use the following project information. Activity Activity Time (weeks) Immediate Predecessor(s) A 4 4 none B 3 C 2 B D 6 B E 3

Use the following project information. Activity

Use the following project information. Activity Activity Time (weeks) Immediate Predecessor(s) A 4 4 none B 3 C 2 B D 6 B E 3 F 4 D G 1 E,F A B E G D F (a) Calculate the completion time for the project. Completion time = weeks