Question: Use the following project information. Activity Time (weeks) Activity A 3 B 4 C 3 D 6 E 4 F 2 G 2 B Immediate

Use the following project information. Activity

Use the following project information. Activity Time (weeks) Activity A 3 B 4 C 3 D 6 E 4 F 2 G 2 B Immediate Predecessor(s) none A B B C D E,F D (a) Calculate the completion time for the project. Completion time = weeks m