Question: Use the following project information. Activity Time (weeks) Immediate Predecessor(s) Activity A 2 none B 3 A 2 B D 4 B E 4 F

Use the following project information. Activity

Use the following project information. Activity Time (weeks) Immediate Predecessor(s) Activity A 2 none B 3 A 2 B D 4 B E 4 F 3 D G 3 E,F A E D TI (a) Calculate the completion time for the project. Completion time = weeks