Question: Use the following project information, Immediate Predecessor(s) Optimistic Time Estimate(weeks) 2. 2.5 5 3 Most Likely Time Estimates (weeks) 3 4 Activity B D E

Use the following project information, Immediate
Use the following project information, Immediate
Use the following project information, Immediate Predecessor(s) Optimistic Time Estimate(weeks) 2. 2.5 5 3 Most Likely Time Estimates (weeks) 3 4 Activity B D E none Pessimistic Time Estimates (weeks) 5 5 8 7 15 8 7 5 4 B - IMO . B.C D 5 5 8 7 4 E F 6 9 12 3 8 G 3 Calculate the expected time for each of the project activities (Round your answers to 2 decimal places, eg. 1.75.) Expected Activity Time A B D E F H