Question: Use the following Table to answer the questions. Activity Predecessor Duration ( weeks ) A - 8 B - 8 C A 6 D A
Use the following Table to answer the questions.
Activity Predecessor Duration weeks
A
B
C A
D A
E B
F D E
G C What is the Late Start, Late Finish for Activity F
What is the Late Start, Late Finish for Activity F