Question: Use the table below to answer all questions: Activity Predecessor Duration ( weeks ) Activity 1 None 3 Activity 2 Activity 1 4 Activity 3

Use the table below to answer all questions:
Activity Predecessor Duration
(weeks)
Activity 1 None 3
Activity 2 Activity 14
Activity 3 Activity 25
Activity 4 Activity 27 What is the Earliest Finish (EF) time for Activity 6?
(A)18 weeks
(B)17 weeks
(C)16 weeks
(D)15 weeks
Activity 6 Activity 41