Question: Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point
Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost (2.5 points)
| Act. | Crash Cost (Slope) | Maximum Crash Time | Normal Time | Normal Cost |
| A | 120 | 2 | 4 | 200 |
| B | 100 | 2 | 4 | 150 |
| C | 90 | 1 | 3 | 140 |
| D | 30 | 1 | 2 | 70 |
| E | 50 | 4 | 6 | 80 |
| F | 60 | 3 | 5 | 120 |
| G | 40 | 2 | 4 | 180 |
| H | 20 | 1 | 2 | 130 |
| E6 |
| G4 |
| D2 |
| B4 |
| A4 |
| Project duration 18 |
| F5 |
| C3 |
| H 2 |
| Total direct cost 1070 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock