Question: Use the process information provided in the following table, when the sequence of flow is A ? B (any machine can be used if available)
Use the process information provided in the following table, when the sequence of flow is A ? B (any machine can be used if available) ? C ? D (any machine can be used if available).
| Operation | Number of Units of Equipment | Design Capacity (by equipment) | Planned Utilization (overall) |
| A | 1 | 255 units/hr | 82.5% |
| B | 4 | 50, 60, 45, 40 | 86.0% |
| C | 1 | 265 units/hr | 60.0% |
| D | 2 | 155, 120 | 87.5% |
|
| |||
Calculate the maximum (design) capacity and effective capacity. (Round "Effective capacity" to 2 decimal places.)