Question: Use the process information provided in the following table, when the sequence of flow is A B (any machine can be used if available) C
| Use the process information provided in the following table, when the sequence of flow is A B (any machine can be used if available) C D (any machine can be used if available). |
| Operation | Number of Units of Equipment | Design Capacity (by equipment) | Planned Utilization (overall) |
| A | 1 | 210 units/hr | 95.0% |
| B | 4 | 160, 150,190, 140 units/hr | 80.0% |
| C | 1 | 220 units/hr | 85.0% |
| D | 2 | 110, 240 | 83.0% |
Calculate the maximum (design) capacity and effective capacity.
Which of the following gives the right values for maximum capacity and effective capacity?
Group of answer choices
210, 287
640, 512
220, 187
None of these are correct