Use the process information provided in the following table, when the sequence of flow is A B (any machine can be used if available) C D (any machine can be used if available). Operation Number of Units of Equipment Design Capacity (by equipment) Planned Utilization (overall) A 1 245 units per hour 92.5% B 4 75, 85, 155, 105 52.0% C 1 450 units per hour 80.0% D 2 300, 250 87.5% Calculate the maximum (design) capacity and effective capacity. Note: Round "Effective capacity" to 2 decimal places