Question: Use this earned schedule table to determine the schedule variance (t) for this project at the end of Month 6. Use this earned schedule table

Use this earned schedule table to determine theUse this earned schedule table to determine the schedule variance (t) for this project at the end of Month 6.

Use this earned schedule table to determine the schedule variance (t) for this project at the end of Month 6. PV ($) Month 1 Month 2 Month 3 Month 4 $125 $275 $500 $875 $50 $120 $255 $420 Month 5 Month 6 Month 7 $1,485 $2,325 $2,670 $715 $865 $0 EV ($ OA) -2.74 B) -3.74 OC) - 1.26 OD) -2.26