Question: Use this earned schedule table to determine the schedule variance ($) for this project at the end of Month 6. PV ($) EV ($) Month

Use this earned schedule table to determine the
Use this earned schedule table to determine the schedule variance ($) for this project at the end of Month 6. PV ($) EV ($) Month 1 $125 $50 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 $275 $500 $875 $1,485 $2,325 $2,670 $120 $255 $420 $715 $865 $0 Select one O A $865 O B. $2325 OC -$865 OD. -$1,460