Question: using aoa, diagram the network described below for frank construction project calculate its critical path and project completion time. activity j nodes 1 - 2

using aoa, diagram the network described below for frank construction project calculate its critical path and project completion time. activity j nodes 1-2 time 10 weeks, activity k nodes 1-3 time 8 weeks, activity L nodes 2-46 weeks, activity m nodes 2-33 weeks, activity n nodes 3-42 weeks, activity o nodes 4-57 weeks, activity p nodes 3-55 weeks