Question: Using A-O-N, diagram the network described below for Samanthas construction project. Calculate its critical path. How long is the minimum duration of this network? Activity
- Using A-O-N, diagram the network described below for Samanthas construction project.
- Calculate its critical path.
- How long is the minimum duration of this network?
| Activity | Predecessor | Time (weeks) |
| J | - | 9 |
| K | J | 9 |
| L | J | 6 |
| M | K | 3 |
| N | K | 2 |
| O | L | 7 |
| P | M, N, O | 4 |