Question: Using A-O-N, diagram the network described below for Samanthas construction project. Calculate its critical path. How long is the minimum duration of this network? Activity

  1. Using A-O-N, diagram the network described below for Samanthas construction project.
    1. Calculate its critical path.
    2. How long is the minimum duration of this network?

Activity Predecessor Time (weeks)
J - 9
K J 9
L J 6
M K 3
N K 2
O L 7
P M, N, O 4

Answer:

  1. Critical Path (number of weeks)
  1. Minimum duration of this network (weeks)

Show your A-O-N diagram here: