Question: Using PERT Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and
Using PERT Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 9. a) The probability that the project will be completed in 12 months = (round your response to four decimal places). b) The probability that the project will be completed in 20 months = round your response to four decimal places). c) The probability that the project will be completed in 24 months = round your response to four decimal places). d) The probability that the project will be completed in 30 months = round your response to four decimal places). e) The due date that yields a 95% chance of completion = 1 months (round your response to two decimal places)