Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is
22
months, and the project variance is
4.
Part 2a) The probability that the project will be completed in
18
months =
0.02280.0228
(round your response to four decimal places).Part 3b) The probability that the project will be completed in
21
months =
0.3085
(round your response to four decimal places).Part 4c) The probability that the project will be completed in
24
months =
0.8413
(round your response to four decimal places).Part 5d) The probability that the project will be completed in
26
months =
0.9772
(round your response to four decimal places).
Part 6e) The due date that yields a 95% chance of completion = ????
enter your response here
months (round your response to two decimal places).