Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and

 Using PERT, Adam Munson was able to determine that the expected
project completion time for the construction of a pleasure yacht is 22

Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and the project variance is 99. The probability that the project will miss a deadline of 24 months is response to two decimal places). (round your 0% 57.93% 50% 100% 42.07%