Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and

 Using PERT, Adam Munson was able to determine that the expected

Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 16. a) The probability that the project will be completed in 5 months = (round your response to four decimal places). b) The probability that the project will be completed in 25 months = (round your response to four decimal places). C) The due date that yields a 95% chance of completion = months (round your response to two decimal places)