Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 16. a) The probability that the project will be completed in 8 months = nothing (round your response to four decimal places). b) The probability that the project will be completed in 23 months = nothing (round your response to four decimal places). c) The probability that the project will be completed in 28 months = nothing (round your response to four decimal places). d) The probability that the project will be completed in 40 months = nothing (round your response to four decimal places). e) The due date that yields a 95% chance of completion = nothing months (round your response to two decimal places).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts