Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 9.
c) The probability that the project will be completed in 27 months = enter your response here
(round your response to four decimal places).