Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is
21
months, and the project variance is
4.
a) The probability that the project will be completed in
17
months =
nothing
(round your response to four decimal places).
b) The probability that the project will be completed in
20
months =
nothing
(round your response to four decimal places).
c) The probability that the project will be completed in
23
months =
nothing
(round your response to four decimal places).
d) The probability that the project will be completed in
25
months =
nothing
(round your response to four decimal places).
e) The due date that yields a 95% chance of completion =
nothing
months (round your response to two decimal places).