Question: Using PERT Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and

Using PERT Adam Munson was able to determine that
Using PERT Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project vanances a) The probability that the project will be completed in 15 months = 0.0000 (round your response to four deomal places) b) The probability that the project will be completed in 23 months - fround your response to four dromal places)