Question: Using Table-1, the earliest start time for activity D is A. 0.0 weeks. B. 9.0 weeks. C. 5.5 weeks. D. 4.0 weeks
Using Table-1, the earliest start time for activity D is A. 0.0 weeks. B. 9.0 weeks. C. 5.5 weeks. D. 4.0 weeks