Question: Using the BOM shown below, A 1 week B (2) 2 weeks OK week D (2) 13 weeks E (4) 2 weeks F (2) 3

Using the BOM shown below, A 1 week B (2) 2 weeks

Using the BOM shown below, A 1 week B (2) 2 weeks OK week D (2) 13 weeks E (4) 2 weeks F (2) 3 weeks C 1) 1 week E (2) 2 weeks What is the cumulative lead time for end item A? Cumulative lead time 11 weeks