Question: Using the cumulative data from the IPMR below for WBS 1.1.5, calculate a formula-based estimate at completion (EAC) using the performance factor of cost performance
Using the cumulative data from the IPMR below for WBS 1.1.5, calculate a formula-based estimate at completion (EAC) using the performance factor of cost performance index times schedule performance index, or CPI x SPI.
WBS number 1.1.5, Armament, has a BCWS of 3049, a BCWP of 2807, an ACWP of 3262, a BAC of 3818, and an EAC of 4510
Please select answer from options below.
| 4538.2 |
| 4436.9 |
| 1275.4 |
| 4358.8 |
Please show work.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
