Question: Using the cumulative data provided from the integrated program Management report, what is the schedule performance index (SPI) for the Armament work Breakdown Structure (WBS)

Using the cumulative data provided from the integrated program Management report, what is the schedule performance index (SPI) for the Armament work Breakdown Structure (WBS) element? Image Description number 1.1.5, Armament, has a BCWS of 3049, A BCWP of 2807, an ACWP of 3262, a BAC of 3818, and an EAC of 4510 1.09 0.93 .086 .092