Question: Using the cumulative data provided from the Integrated Program Management Report, what is the schedule performance index (SPI) for the Armament Work Breakdown Structure (WBS)
| Using the cumulative data provided from the Integrated Program Management Report, what is the schedule performance index (SPI) for the Armament Work Breakdown Structure (WBS) element? (IMAGE DESCRIPTION: WBS number 1.1.5, Armament, has a BCWS of 3049, a BCWP of 2807, an ACWP of 3262, a BAC of 3818, and an EAC of 4510.) |
| 0.92 |
| 0.86 |
| 1.09 |
0.93 |