Question: Using the data attached: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d. What is

Using the data attached:

a. Draw a project network.

b. What is the critical path?

c. What is the normal project cost?

d. What is the total cost of the project if you need to crash it by 1 week?

Using the data attached: a. Draw a project

Activity Predecessors Normal Cost Crash Cost Normal Time (Wks) 5 Crash Time (Wks) 4 . B . 8 6 6 D 5 7 6 8 3 B,D,C 6 E F G $400 1600 800 600 1200 800 500 400 900 $750 2200 1100 1000 2200 1000 650 600 1300 D 2 3 2 H D E F,G,H 4 3 6 5