Question: Using the data attached: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d. What is

Using the data attached:

a. Draw a project network.

b. What is the critical path?

c. What is the normal project cost?

d. What is the total cost of the project if you need to crash it by 1 week?

Chp 19 #40 Activity Predecessor(s) Normal Time (Wks) Crash Time (Wks) Normal Cost Crash Cost A --- 5 4 $400 $750 B A 8 6 1600 2200 C A 7 6 800 1100 D -- 6 5 600 1000 E B,D,C 8 6 1200 2200 F D 3 2 800 1000 G D 3 2 500 650 H E 4 3 400 600 I F,G,H 6 5 900 1300