Question: Using the data below, find the EOQ, the total annual cost associated with the economic order quantity, and the reorder point. Annual Demand: 8,000 units
Annual Demand: 8,000 units
Weeks Operating: 52/year
Ordering Cost: $35/order
Holding Cost: $4/unit/year
Lead-Time: 3 weeks
Step by Step Solution
3.31 Rating (157 Votes )
There are 3 Steps involved in it
EOQ2DEMANDORDERING COSTHOLDING COST 28000354 5600004 374 UNI... View full answer