Question: Using the following information: Build a network diagram Identify the early start, early finish, late start late finish for each activity Identify the critical path
Using the following information:
- Build a network diagram
- Identify the early start, early finish, late start late finish for each activity
- Identify the critical path
- Identify the duration of the critical path
- What is the float of Activity B
- What is the float of Activity H
| Activity | Predecessor | Duration in Days |
| A | Start | 3 |
| B | Start | 6 |
| c | A, B | 12 |
| D | B | 5 |
| E | D | 4 |
| F | C | 6 |
| G | E,F | 8 |
| H | E | 7 |
| I | H | 3 |