Question: Using the following information develop a Gantt chart Optimistic Estimate Pessimistic Estimate Most Likely Estimate Application 1 4 months 9 months 6 months Application 2
Using the following information develop a Gantt chart
| Optimistic Estimate | Pessimistic Estimate | Most Likely Estimate | |
| Application 1 | 4 months | 9 months | 6 months |
| Application 2 | 1 month | 5 months | 3 months |
| Application 3 | 5 months | 10 months | 7 months |
| Application 4 | 1 month | 7 months | 4 months |
| Application 5 | 5 months | 10 months | 8 months |
| Application 6 | 2 months | 9 months | 5 months |
| Application 7 | 5 months | 12 months | 7 months |
| Application 8 | 3 months | 13 months | 9 months |
| Application 9 | 4 months | 11 months | 8 months |