Question: Using the following information develop a Gantt chart. Optimistic Estimate Pessimistic Estimate Most Likely Estimate Application 1 11 13 12 Application 2 9 11 10
Using the following information develop a Gantt chart.
| Optimistic Estimate | Pessimistic Estimate | Most Likely Estimate | |
| Application 1 | 11 | 13 | 12 |
| Application 2 | 9 | 11 | 10 |
| Application 3 | 12 | 14 | 13 |
| Application 4 | 8 | 10 | 9 |
| Application 5 | 13 | 16 | 14 |
| Application 6 | 9 | 11 | 10 |
| Application 7 | 8 | 10 | 9 |
| Application 8 | 16 | 19 | 18 |
| Application 9 | 15 | 18 | 17 |
Describe 2 strategies you can use to bring the project timeline to 12 months.