Question: Using the following project information, calculate the expected time for each of the project activities. Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic
Using the following project information, calculate the expected time for each of the project activities.
| Activity | Optimistic Time Estimate(weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) | Immediate Predecessor(s) | ||||
| A | 2 | 7 | 10 | none | ||||
| B | 3 | 4 | 8 | A | ||||
| C | 5 | 7 | 13 | A | ||||
| D | 5 | 5 | 12 | B | ||||
| E | 6 | 9 | 17 | C | ||||
| F | 4 | 5 | 5 | D,E | ||||
| G | 2 | 6 | 10 | D,E | ||||
| H | 4 | 5 | 11 | F | ||||
| I | 6 | 8 | 13 | G | ||||
| J | 3 | 3 | 3 | H,I | ||||
(Round your answers to 2 decimal places, the tolerance is +/-0.01)
| Activity | Expected Time |
| A | |
| B | |
| C | |
| D | |
| E | |
| F | |
| G | |
| H | |
| I | |
| J | |