Question: Using the following project information Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 3 5 none
Using the following project information
| Activity | Optimistic Time Estimate(weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) | Immediate Predecessor(s) | ||||
|---|---|---|---|---|---|---|---|---|
| A | 2 | 3 | 5 | none | ||||
| B | 2.6 | 4 | 5 | A | ||||
| C | 5 | 7 | 8 | A | ||||
| D | 3 | 5 | 8 | B, C | ||||
| E | 4 | 6 | 13 | B, C | ||||
| F | 2 | 5 | 8 | D | ||||
| G | 4 | 5 | 7 | E | ||||
| H | 6 | 6 | 9 | F | ||||
| I | 4 | 8 | 11 | G | ||||
| J | 2 | 3 | 3 | H, I |
The critical path is A-C-E-G-I-J.
| Activity | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
| Variance | 0.25 | 0.16 | 0.25 | 0.69 | 2.25 | 1.00 | 0.25 | 0.25 | 1.36 | 0.03 |
(a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project 31) =
(b) Calculate the probability that the project will be completed in 35 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project 35) =
please explain your answer