Question: Using the information given, calculate the replenishment time when no beginning inventory exists. Immediate Parent Leed Time (weeks) Component A 1 B A 2 A

Using the information given, calculate the

Using the information given, calculate the replenishment time when no beginning inventory exists. Immediate Parent Leed Time (weeks) Component A 1 B A 2 A 1 D A 4 E A 2 F B 4 B 1 H D 2 I D 4. E 4 E 2 J K L M E 2 F 1 N F 2 o H 3 K 1 Q K 1 A B D G I K L M N O Q The cumulative lead time, the longest planned length of time to complete the end product, is weeks