Question: Using the information on the table below, what would happen to the project if activity G gets delay by 5 time units. table [

Using the information on the table below, what would happen to the project if activity G gets delay by 5 time units.
\table[[Activity Predecessor,Estimated],[A,-,5],[B,A,5],[C,A,6],[D,B,C,13],[L,B,6],[,D,4],[G,C,9],[H,E,F,G,2]]
Project gets delay by 2 weeks
Critical path will expanded 5 time units
Project would explode in pieces
Project will still be completed on time