Question: Using the information provided in the table below, do the following: a . Construct a network diagram. b . Determine which activities are on the

Using the information provided in the table below, do the following:
a. Construct a network diagram.
b. Determine which activities are on the critical path.
c. Compute the length of the critical path.
\table[[Activity,Estimated time (days)],[1->2,5],[2->3,6],[2->4,4],[3->6,9],[6->7,2],[4->5,4],[4->7,18],[5->7,10]]