Question: Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project

Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way.

Activity

Normal Time (weeks)

Normal Cost ($)

Crash Time (weeks)

Crash Cost ($)

Maximum weeks Reduced

Crash Cost per Week ($)

A

3 500 2 900 1 400

B

4 600 3 700 1 100

C

6 800 3 1,340 3 180

D

6 1,500 4 2,150 2 325

E

6 1,750 4 2,250 2 250

F

5 1,200 5 1,200 0 0

G

7 1,500 5 1,830 2 165

H

3 500 3 500 0 0

Using the information provided in the table, the

Reduce G ---------------------C by ------------------- weeks , at cost of $ .-------------------

B(4) E(6) A(3) C[6) G(7) H(3) D(6) F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!