Question: 8. Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the
8. Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way.
| Activity | Normal Time (weeks) | Normal Cost ($) | Crash Time (weeks) | Crash Cost ($) | Maximum weeks Reduced | Crash Cost per Week ($) | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A | 3 | 500 | 2 | 900 | 1 | 400 | ||||||
| B | 4 | 600 | 3 | 700 | 1 | 100 | ||||||
| C | 6 | 800 | 3 | 1,280 | 3 | 160.00 | ||||||
| D | 6 | 1,500 | 4 | 2,150 | 2 | 325 | ||||||
| E | 6 | 1,750 | 4 | 2,250 | 2 | 250 | ||||||
| F | 5 | 1,200 | 5 | 1,200 | 0 | 0 | ||||||
| G | 7 | 1,500 | 5 | 1,790 | 2 | 145 | ||||||
| H | 3 | 500 | 3 | 500 | 0 | 0 |
Reduce G by ___(1,0,2,3)____ weeks, C by _____(1,2,4,0)_____ weeks, at a cost of $ _________