Question: Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? A
Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? A B C D E Activity t 5 4 3 3 2 LL (c) Determine the critical path? (d) State the non-critical activities. (e) What is the implication of allowing activity B to spend extra 2 days instead of the slack number of days given in the table. G 1 10 9 A 5 C 3 ES 5 2 D3 4 B 4 EF 19 E 2 F 10 LS LO 6 3 G 9 LF 19 5 Slack 1 Critical Y
Step by Step Solution
There are 3 Steps involved in it
Based on the project network diagram provided lets solve each of the questions step by step using the Early Start ES Early Finish EF Late Start LS and Late Finish LF method a Complete the table below ... View full answer