Question: Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? (c) Determine

Using the method of ES, EF, LS, and LF; (a)
Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? (c) Determine the critical path? (d) State the non-critical activities. (e) What is the implication of allowing activity B to spend extra 2 days instead of the slack number of days given in the table. B () 5 4 D3 E G C 3 2 E 10 ES EF LS LF Slack Critical I 6 1 Activity A B D E F G t 5 4 3 3 2 10 9 5 19 19 Y

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!