Question: questions A to E Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete

questions A to E questions A to E Using the method of ES, EF, LS,
Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? (c) Determine the critical path? (d) State the non-critical activities. (e) What is the implication of allowing activity B to spend extra 2 days instead of the slack number of days given in the table. B A 5 2 4 d3 E G 3 2 10 ES EF LS LF Slack Critical 6 1 Activity B D E F G t 5 4 3 3 2 10 9 5 19 19 Y