Question: Using the network diagram only ,find Shortest taskfirst Minimum slackfirst Most criticalfollowers Mostsuccessors Using the network diagram and the additional information below,find The crash cost
- Using the network diagram only ,find
- Shortest taskfirst
- Minimum slackfirst
- Most criticalfollowers
- Mostsuccessors
- Using the network diagram and the additional information below,find
- The crash cost perday
- Which activities should be crashed to meet a project deadline of 13 daysat minimum cost. Assume partial crashing isallowed.
- Reconsider Question 2 above, assuming a fixed overhead cost of $30 per day but no project deadline. What is the leastcost crash program? What if the overhead costwas
$40? What if it was $60?

Activity| Crash Time (days)|Crashed Cost (total) [Normal Time (days) Normal Cost A 3 $500 4 $300 B 1 925 3 250 C 4 550 7 400 D 3 250 5 150