Question: Using the network diagram only ,find Shortest taskfirst Minimum slackfirst Most criticalfollowers Mostsuccessors Using the network diagram and the additional information below,find The crash cost

  1. Using the network diagram only ,find
    1. Shortest taskfirst
    2. Minimum slackfirst
    3. Most criticalfollowers
    4. Mostsuccessors

  1. Using the network diagram and the additional information below,find
    1. The crash cost perday
    2. Which activities should be crashed to meet a project deadline of 13 daysat minimum cost. Assume partial crashing isallowed.

  1. Reconsider Question 2 above, assuming a fixed overhead cost of $30 per day but no project deadline. What is the leastcost crash program? What if the overhead costwas

$40? What if it was $60?

Using the network diagram only ,findShortest taskfirstMinimum slackfirstMost criticalfollowersMostsuccessorsUsing the network diagram

Activity| Crash Time (days)|Crashed Cost (total) [Normal Time (days) Normal Cost A 3 $500 4 $300 B 1 925 3 250 C 4 550 7 400 D 3 250 5 150

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!