Question: Using the PERT method review the following data for a project that should be scheduled using CPM:IMMEDIATE PREDECESSORS TIMES ( DAYS ) ACTIVITY a m

Using the PERT method review the following data for a project that should be scheduled using CPM:IMMEDIATE PREDECESSORS TIMES (DAYS)ACTIVITY a m bA 147B 135C A 2511D A 189E B 123F C,D 1611G D,E 123H F,G 233b. What is the critical path?multiple choiceA-D-G-HA-D-F-HB-E-G-HA-C-F-Hc. What is the expected project completion time? (Round your answer to 3 decimal places.)Project completion timedaysd. What is the probability of completing this project within 22 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)Probability