Question: Using the PERT method review the following data for a project that should be scheduled using CPM:IMMEDIATE PREDECESSORS TIMES ( DAYS ) ACTIVITY a m
Using the PERT method review the following data for a project that should be scheduled using CPM:IMMEDIATE PREDECESSORS TIMES DAYSACTIVITY a m bA B C A D A E B F CD G DE H FG b What is the critical path?multiple choiceADGHADFHBEGHACFHc What is the expected project completion time? Round your answer to decimal places.Project completion timedaysd. What is the probability of completing this project within days? Do not round intermediate calculations. Round your answer to decimal places.Probability
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
