Question: Using the Power - Interest Grid, the project manager should have the following relationship with a low power, low interest stakeholder Question 3 options: keep

Using the Power-Interest Grid, the project manager should have the following relationship with a low power, low interest stakeholder
Question 3 options:
keep informed
closely manage
monitor
keep satisfied